Rocklin Pipeline Replacement Project


Midas Main Road Construction flier
Providing Long-Term Water Reliability for Rocklin Residents

Placer County Water Agency (PCWA) is undertaking a crucial infrastructure project to replace an aging water main along Midas Avenue between 2nd Street and Argonaut Road in the City of Rocklin.

The existing steel pipes, installed in 1963 and coated with cement mortar, are approaching the end of their operational lifespan. A series of leaks and failures on the mainline pipes in recent years has underscored the importance of this project to maintaining the consistent delivery of safe drinking water to Rocklin residents.

Project Scope:

Phase 1 of this project focuses on replacing a significant portion of the mainline pipes along Midas Avenue. The project included trenching to install a new 12” mainline pipe, service laterals, and meter boxes. After pressurizing the mainline and connecting individual residences, crews backfilled the trench and applied temporary pavement. Final paving and striping will be completed once the entire road section is ready. The project will progress in sections along the route to minimize disruption.

Traffic Impacts:

Northbound Midas Ave will be closed from Pacific St. to Argonaut Ave until that section is complete.

Southbound Midas Ave will remain open. (Southbound Midas Ave will be closed for paving upon completion of paving the Northbound lane.)

Flaggers will be present to safely control traffic flow.

Expect delays while traveling through the construction zone. Motorists should consider alternate routes.

Project Timeline:

Phase 1 began in October 2024 and is projected to conclude by early Summer 2025.

Expected Timeline for Paving:

Work begins April 14, and may last through May 9.


Background

Originally scheduled to start in August 2023, Phase 1 was delayed due to supply chain issues involving critical components, such as brass fittings and valves. In addition, in light of the significant disruptions caused by the severe storms of 2023, PCWA strategically reconfigured the project timeline to lessen inconveniences for residents. As a result, Phase 2, which focused on the pipeline section between Clover Valley and Argonaut Road, was initiated first and successfully completed in July 2024.

With an estimated cost of $3.1 million for Phase 1, the overall multi-phase project is expected to total $24 million when finished. This investment, funded by PCWA ratepayers and the City of Rocklin, will provide Rocklin with a modern and reliable water infrastructure system that will last for decades.

More Information:

For questions, contact Project Manager Steve Bowman at (530) 823-4881 or sbowman@pcwa.net. Additional information about the Midas Main Replacement Projects is available on our Construction Projects page at: https://www.pcwa.net/about-pcwa/projects

Midas Main Road Construction flier

Project Schedule

Phase 1

  • Begin Construction: Fall 2024
  • End Construction: Spring 2025

Phase 2

  • Construction Completed: Summer 2024